The Party Wall etc. Act 1996 creates procedures for certain types of building work that may affect neighbouring property.
The principal categories are:
- Section 1: construction of a new wall at or astride the line of junction between properties.
- Section 2: certain works to an existing party wall, party structure or party fence wall.
- Section 6: certain excavations close to neighbouring buildings or structures.
Not every wall on a boundary is a party wall, and not every extension or excavation falls within the Act. The proposed construction needs to be considered against the statutory criteria.
When Might the Party Wall Act Apply?
Common examples include:
- Cutting into a party wall to insert beams or structural supports.
- Raising, rebuilding or thickening a party wall.
- Removing chimney breasts from a party wall.
- Repairing or rebuilding certain party structures.
- Constructing a new wall on or at the boundary.
- Excavating close to a neighbouring building where the excavation is deeper than the neighbour’s foundations and falls within the distances and geometrical tests set out by the Act.
Loft conversions, rear extensions and basement works frequently raise Party Wall considerations, although the Act does not automatically apply simply because one of these projects is proposed.
The 3-Metre and 6-Metre Excavation Rules
The excavation provisions are often misunderstood.
The Act may apply where excavation is proposed:
- Within 3 metres of an adjoining owner’s building or structure and the proposed excavation will extend below the level of the adjoining owner’s foundations.
- Within 6 metres in certain circumstances where the proposed excavation intersects a defined plane measured from the adjoining owner’s foundations.
Whether Section 6 applies therefore depends upon both distance and excavation depth, not distance alone.
When Should Party Wall Matters Be Considered?
Party Wall issues should ideally be identified while the project is still being designed.
This allows sufficient time for:
- Review of drawings and foundation proposals.
- Identification of affected adjoining owners.
- Preparation and service of the appropriate notices.
- Surveyor appointments where required.
- Schedules of condition.
- Agreement or determination of the Party Wall Award before notifiable work begins.
Leaving the process until immediately before construction can cause avoidable delay.
Party Wall Notices
The notice required depends upon the work being undertaken.
Broadly, the statutory notice periods include:
- Party structure works: normally at least two months before the work is intended to begin.
- Line of junction works: normally at least one month.
- Adjacent excavation works: normally at least one month.
The notice must contain the information required by the relevant part of the Act. Poorly prepared or incorrectly served notices can complicate the process, so professional advice may be useful where the position is uncertain.
What Happens After a Notice Is Served?
The procedure depends upon the type of notice and the adjoining owner’s response.
For party structure works, an adjoining owner may consent to the work or dissent. If the statutory dispute procedure is engaged, surveyors can be appointed under Section 10 of the Act.
The parties can either:
- appoint one Agreed Surveyor; or
- appoint a surveyor each.
The appointed surveyor or surveyors act within the statutory framework of the Act. Their role is not simply to represent one party in the ordinary sense, but to resolve the matters properly arising under the Act.
What Is a Party Wall Award?
A Party Wall Award records the matters determined by the appointed surveyor or surveyors.
Depending upon the works, it may address:
- The notifiable works permitted under the Act.
- The manner in which those works should be undertaken.
- Working hours or access arrangements where relevant.
- Protective measures.
- Drawings and construction details.
- A Schedule of Condition.
- Other matters properly arising under the Act.
The Award provides a formal framework within which the relevant works can proceed.
What Is a Schedule of Condition?
A Schedule of Condition records the visible condition of the adjoining property before relevant construction work begins.
It commonly includes written observations and photographs of:
- Existing cracking.
- Decorative finishes.
- Walls and ceilings.
- Floors.
- External elevations.
- Other areas potentially affected by the proposed work.
The schedule can provide useful evidence if there is later disagreement about whether damage existed before the works began.